LEA VILLAGE – FLOOD ALLEVIATION SCHEME – JANUARY/FEBRUARY 2021
A40/B4222 Lea Village Flood Alleviation Works
Road closed Monday, 11 January 2021 to (and including) Thursday, 25 February 2021
Road closed 24 hours each day, 7 days a week
Please refer to the programme of works below:
A40 Phase
Works between Crown Barns and Old Mill Lane crossing the A40
Full Road closure between Monday, 11 January 2021 and Friday, 19 February2021
The road will be closed 24 hours each day including weekends
Old Mill Lane Phase
The road will be closed 24 hours each day including weekends
Main Programme Dates:
Old Mill Lane adjacent to A40 ( Between Brook House and Derwent House )
Full Road closure between Wednesday, 20 January 2021 and Wednesday, 27 January 2021
Works along Old Mill Lane between Brook House and B4222:
Main Deep Drainage run : road closed from Wednesday, 27 January to (and including) Friday, 5 February 2021.
Secondary Pipework (new gullies, connections and access chambers ) : road closed from Saturday, 6 February 2021 to (and including) Monday, 22 February 2021.
Resurfacing of Old Mill Lane : road closed from Tuesday, 23 February 2021 until (and including) Thursday, 25 February 2021.