LEA VILLAGE – FLOOD ALLEVIATION SCHEME – JANUARY/FEBRUARY 2021

A40/B4222 Lea Village Flood Alleviation Works

Road closed Monday, 11 January 2021 to (and including) Thursday, 25 February 2021

Road closed 24 hours each day, 7 days a week

Please refer to the programme of works below:

A40 Phase

Works between Crown Barns and Old Mill Lane crossing the A40  

Full Road closure between Monday, 11 January 2021 and Friday, 19 February2021

The road will be closed 24 hours each day including weekends

Old Mill Lane Phase

The road will be closed 24 hours each day including weekends

Main Programme Dates:

Old Mill Lane adjacent to A40 ( Between Brook House and Derwent House )

Full Road closure between Wednesday, 20 January 2021 and Wednesday, 27 January 2021

Works along Old Mill Lane between Brook House and B4222:

Main Deep Drainage run : road closed from Wednesday, 27 January to (and including) Friday, 5 February 2021.

Secondary Pipework (new gullies, connections and access chambers ) : road closed from Saturday, 6 February 2021 to (and including) Monday, 22 February 2021.

Resurfacing of Old Mill Lane : road closed from Tuesday, 23 February 2021 until (and including) Thursday, 25 February 2021.

Diversion map
HGV Diversion map

0 Comments

There are no comments yet

Leave a comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Skip to content