ROAD CLOSURES – OCTOBER 2020 – 09.10.2020
Highway Works – Resurfacing Works
A44 – Docklow to Newhampton Farm – Revised end date
Monday, 5 October 2020 to (and including) Friday, 16 October 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
B4347 – B4348 Junction to Chanstone Mill – Revised dates
Thursday, 8 October 2020 to (and including) Friday, 16 October 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
A480 – Station Road to Brinsop Turn, Credenhill – Revised end date/times
Friday, 9 October 2020 to (and including) Thursday, 15 October 2020
Road closed 09.30 hours to 15.30 hours daily (restricted hours) – No weekend working
Traffic signals will be in operation on Friday, 16 October 2020
B4347 – Pontipina SD Joint to Blackbush – Revised end date
Friday, 9 October 2020 to (and including) Friday, 16 October 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
A438 – Tarrington to Ledbury Lodge – New
Monday, 12 October 2020 to (and including) Tuesday, 20 October 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
Please refer to attached diversion route plan.
A438 – C1097 to Surface Joint, Byford – Revised dates
Friday, 16 October 2020 to (and including) Tuesday, 20 October 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
Traffic signals will be in operation on Wednesday, 21 October and Thursday, 22 October 2020
A4137 – Burnthouse Green to Pigeon House – Revised end date
Friday, 16 October 2020 to (and including) Friday, 23 October 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
A438 – Tin Hill to Red Ley – Revised dates
Wednesday, 21 October 2020 to (and including) Monday, 26 October 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
Traffic signals will be in operation on Tuesday, 21 October 2020
A44 – Legions Cross towards Pembridge – Revised dates
Tuesday, 13 October 2020 to (and including) Tuesday, 20 October 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
A44 – Stanner – NIGHT WORKS – Revised end date
Thursday, 22 October 2020 to (and including) Monday, 26 October 2020
Road closed 20.00 hours to 06.00 hours each evening – No weekend working
A44 – C1081 to Beech Tree Cottage – Revised end date
Friday, 23 October 2020 to (and including) Friday, 30 October 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
A417 – Ullingswick Turn to Marsh Farm – Revised dates
Wednesday, 21 October 2020 to (and including) Friday, 30 October 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
A40 – Weston under Penyard
Monday, 26 October 2020 to (and including) Friday, 6 November 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
Traffic signals will be in operation from Tuesday, 13 October 2020 until (and including) Sunday, 25 October 2020
B4348 – Vowchurch Accident Site to Cockyard Turn – Revised dates
Monday, 26 October 2020 to (and including) Tuesday, 3 November 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
A44 – Bend approaching C1031 Crossroads from Lyonshall – Revised dates
Thursday, 29 October 2020 to (and including) Thursday, 5 November 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
A417 – Hillhampton to Burley Gate
Friday, 30 October 2020 to (and including) Friday, 6 November 2020
Road closed 09.00 hours to 17.00 hours daily – No weekend working
New Roundabout Construction
A4110/B4529 Lawtons Cross, Mortimer
Roads closed from Monday, 24 August 2020 to (and including) Friday, 30 October 2020
A combination of phased road closures 24/7 and traffic signals will be in operation, as follows:
Phase 1: B4529 closure west of junction with A4110 – Complete
Monday, 24 August 2020 to Friday, 18 September 2020
Phase 2: B4529 closure east of junction with A4110
Tuesday, 22 September 2020 to Friday, 16 October 2020
Phase 3: A4110 north of junction with B4529
Monday, 5 October 2020 to Friday, 23 October 2020
Phase 4: A4110 south of junction with B4539
Monday, 5 October 2020 to Friday, 30 October 2020
Drainage Works
A40 Lea Village Drainage Scheme
Millbrook Gardens – rolling closure
Monday, 5 October 2020 until 6 November 2020
09.00 hours to 17.00 hours daily
B4222
16 November 2020 to (and including) 20 November 2020
Lea Crossroads (Old Mill Lane – single track cul-de-sac)
23 November 2020 to (and including) 26 February 2021 although we will look to re-open during the Christmas period (between
14 December 2020 and 18 January 2021)
Bridge Works
U65607 – Paunton Lane, Paunton Bridge
Monday, 26 October 2020 and Tuesday, 27 October 2020
Road closed 08.00 hours on 26 October and will not re-open until 17.00 hours on 27 October 2020
Removal of vegetation and loose debris from riverbank
Other Road Closures
B4260 – Wilton Road, Ross on Wye
Monday, 26 October 2020 to (and including) Friday, 30 October 2020
Road closed from 08.00 hours on 26 October 2020 and will not re-open until 17.00 hours on 30 October 2020
Inspection of rock face and crest above Wilton Road. Removal of vegetation at the base of the rock face.
C1257 – Symonds Yat West Road (Ferrie Lane)
Road closed until further notice
B4224 – Fiddlers Green, Fownhope
Structural wall failure and landslip
Full road closure in place until 31 December 2020
U71411 – Garway Court Lane – Revised date
Carriageway deterioration
Full road closure in place until Friday, 4 December 2020
0 Comments